In just a few short weeks our new hospital will be complete. we spent the past week watching dry wall go up and all air con ducts placed. I firmed up the order for all surgical lighting and treatment tables and walked the project this weekend with our client Randy Harmon who will be installing the data and security cameras throughout the hospital. We have a meeting with the landscaper tomorrow and still need to decided on what type of flooring to be used in the back treatment area of the hospital. One HUGE hurdle Paul and Jeff tackled this week was working with Edison to allow our new electrical service to be installed directly from Crenshaw overhead rather than us having to fund 300′ underground trench. These dudes took care of it and now we stomp on the accelerator and keep going!!